GERMANY (News release) -- On Sunday 14. October 2018 at around 10:00 a fire broke out in the main fibre spinning area at Kelheim Fibres GmbH. The fire was extinguished by 13:00 by the company's own fire brigade with the support of local fire services. No employees were seriously injured, one suffered minor injuries. There were no hazardous discharges to the environment.
Following a first preliminary assessment of the damage caused, a provisional plan for the restart of the production lines has been developed. It is planned to start the first two lines at the end of October 2018, with a further two to follow at the end of November 2018. After four months, it is planned to have started a further four lines, with the remaining two to follow eight months later. Kelheim Fibres is in direct contact with customers and has informed them of the expected impact on supply.